National Grid Gas Main Project Update & Schedule for May 1st through 3rd

ALL VEHICLES MUST BE REMOVED FROM WEST STREET, HIGH STREET AND BLEECKER STREET BY 8:00 A.M. WEDNESDAY MORNING FOR POST CONSTRUCTION STREET CLEANING

Additional parking restrictions:

Monday 5/1

Bleeker St from James St to George St
West side of Paine St from Bleeker St to Arch St

Tuesday 5/2

Bleeker St from James St to George St
West side of Paine St from Bleeker St to Arch St

Wednesday 5/3

West side of Paine St from Bleeker St to Arch St for main project

Street blocks will be closed except for local traffic while we are working in the area.

Individual gas service line replacement will begin on Monday 5/1 starting on West St. All personnel must carry identification. Please be sure that they present it before letting anyone into your home. If you suspect that something doesn’t seem right, call 9-1-1 for the Green Island Police immediately and they will check things out.

Vehicles must be moved so that damage does not occur. If you have any questions, please call National Grid at 1-800-642-4272.