National Grid service line replacement* will continue on High Street next week (South of Arch Street).
They will also be starting Paine Street services on Monday with a second crew, starting at Bleeker Street and working their way South.
Once the crew on High Street finishes they will move to finish the services on Bleeker Street and then team up with the crew on Paine Street.
Retirements of old mains are scheduled to start the week of 6/5.
Streets will be closed except for local traffic only when crews are working in the area.
*All service crew personnel must carry identification. Please be sure that they present it before letting anyone into your home. If you suspect that something doesn’t seem right, call 9-1-1 for the Green Island Police immediately and they will check things out.
Vehicles should be moved from the construction area so that damage does not occur. If you have any questions, please call National Grid at 1-800-642-4272.